AAVSO's Morgan 24" Cassegrain
Formerly located at lowell Observatory, Flagstaff Arizona

Return to Telescope Page   Return to Photo Gallery Page
The Morgan 24" Cassegrain telescope was formerly located in the Lowell Observatory's Visitor Center Lowell Observatory in Flagstaff Arizona. The American Association of Variable Stars (AAVSO), under the direction of Arne Henden, received a donation of the telescope and the search then began for a site on which to put the telescope. During one meeting of the Society of Astronomical Sciences (SAS) Thomas Smith, Director of the Dark Ridge Observatory, was approached as a possible site for placement. Subsequent to that discussion it was agreed that the Morgan telescope would be relocated to Dark Ridge Observatory, outside of Weed, New Mexico, for rebuild, siting and operation.

The telescope remains in storage on site at DRO as the roll-off observatory building is being constructed.

Below is the on-going historical records of the rebuild effort and the construction of the new home for the Morgan 24" Cassegrain Telescope.



The rebuilding of the Morgan 24" Cassegrain (click the image for a larger view)
May 03, 2009 A closer look This is a closer look at the top of the OTA and gantry crane. There is currently about 18" clearance to the roof but that will change with base lift.
May 03, 2009 RA gross alignment The telescope polar end support has been raised to the latatude of the telescope so that measurements can be taken for base lift and clearnce to roof.
May 03, 2009 Optics in observatory The two secondary cages with their secondary mirrors and the primary mirror cell with mirror have been place into the observatory awaiting installation.
May 01, 2009 RA drive assembly The RA drive assembly has been relocated into the shop in preparation for rebuild and modifications to accept the Siderial Technolgy servo drive control system. New bearings and gears will be installed along with the necessary gear housing fabrication.
March 08, 2009 Morgan OTA mounted The telescope tube was remounted without optics for the initial purpose of performing a gross pointing of the RA axis to near the pole and to determing the lift needed to acheive the minimum desired altitude observing angle.
March 04, 2009< Another at "home" view/td> This is another view of the Morgan inside the observatory showing more details of the gantry and roof clearance before adjusting the RA axis to polar pointing.
March 04, 2009 Morgan shell at "home" The Morgan telescope mount and telescope tube was moved into the completed observatory building along with the 2-ton gantry crane for performing assembly and maintenance.
2/15/2009 South wall and crank The south wall is designed to be manaully lowered if for some unusual reason a more southern view is required. The wall segment is about 250 pounds so I installed a charnk hoist to assist in the lowering and raising. Without this assist I can not overcome the angle and weight of the wall. It will lower to a 90 degree down position at which point it contacts and lays across installed support beams.
1/15/2009 Structure complete This shows the completed observatory structure. The electrical and Ethernet has been installed and all that remains is to motorize the roof and rebuild the scope inside.
1/21/2009 Roof sheeting The roof sheeting has been started. There was quite a delay in this process as the winds were high for the past couple of weeks and handling 3'X10' roof sheetmetal is dangerous in the wind and especially working alone.
1/14/2009 Truss' The roof truss' have been installed. From this point it looks as though the inside concrete to roof apex will be approximately 14 feet in height.
12/19/2009 Roof roll direction As can be seen in this photo, the roof rolls off to the north towards the control room. The total roof roll is just under 20 feet allowing for the best north view as is possible with the spacing requirements.
12/19/2009 Roof walls Here the roof wall sections have been installed making the roof 4 feet taller than the main walls themselves
12/07/2009 Roof framing This shows the begining of the roof structure with the roller wheels
12/04/2009 Roof Rails The piers for the roof rails and the rails themselves have been installed
11/19/2008 Framing begins The basic wall framing and siding has been constructed.
9/12/08 Poured and curing This is the completed slab that the Morgan will rest upon. The radian cooling tubes are visible on the northwest end. In the background is the construction effort for the DRO 20" RC observatory building.
9/10/08 Concrete pouring With help from Jerry Miller (left) and my son Bryan (right) we are pouring the concrete slab and screeing it off level.
9/10/08 Concrete arrives It isn't an easy task to get the concrete truck with 9 yards of concrete up on the ridge but they seem to manage in the mountains just fine.
9/6/08 Under concrete cooling I have installed PEX tubing for use as a cooling system for the concrete. I doubt I will need to use this but now is the time to install it just in case.
9/2/08 Rebar matrix installed The slab base is smoothed and covered with fine dirt and the rebar matrix is installed.
8/29/08 Another view It seems that the concrete block manufacturers that I deal with don't make a block designed to act as a form for a slab. As such I had to manually cut each block to create the form.
Here you can see the completed control room and one of the existing 14" telescope roll-off observatories. This is a view to the north.
8/29/08 Block wall With the concrete footings poured it was time to build the block wall forms in which to pour the concrete slab.
8/26/08 Footing trenches The footings were initially started by hand using a pick and shovel but that quickly came to a halt with the broken pick. Someone put some rocks on top of this ridge, all over it in fact!
8/26/08 Construction begins The start of the construction of the 12' X 16' roll-off observatory for the Morgan begins.
8/2/08 36" RA worm gear Here is seen the RA worm gear and the declination gear housing. The RA worm gear is a 256 tooth brass-bronze gear about 3 inches thick. The optical telescope tube (OTA) mounting flange is shown with mounting bolts installed.
6/30/08 Mission accomplished The happy crew of the unloading party; Jerry Miller, Russ Wright, Tom Smith and Michael Hernandez (left to right).
6/30/08 Easy does it The massive mounting is being eased into the shop. This unit weighs in around 1500 pounds as viewed.
6/30/08 Unloading the beast After the removal of the OTA the telescope mounting was unloaded into the DRO shop for storage and rebuild.
6/25/08 Tom and the scope Tom Smith, Director of Dark Ridge Observatory, poses with the newly arrived Morgan 24" telescope.
6/25/08 The shop and home This perspective shows the shop in the immediate background and further on is the observatory location.
6/25/08 1st day onsite Arrives for rebuild and placement on the Dark Ridge Observatory's ridge top in Weed, New Mexico.

Last update May 03, 2009